Finally a really nice day! There is a lot getting accomplished at KSL. The floor framing for Lot 5 is underway. The brick veneer is going on Lot 6. The cedar shake roof and rough-ins are proceeding on Lot 7. It is really starting to come together. Once we have a few homes up, the final look of KSL will be apparent to all. Very exciting!
The framing on the first KSL home is finished (Lot 7) and the plumbing is being roughed in. The floor system for Lot 6 is beginning and walls should start next week. Lot 5 is ready to start framing in about 30 days. Finally, we have had enough dry weather to get the lumber delivered to the site. It’s going to look great!
The rain will not let up. Every third day we get enough rain to make a mess. Fortunately, we have installed a huge amount of gravel on the main road so that we can get in and out of the site to work. Nonetheless, we are making headway on Lot 7 and the framing on Lot 6 should start late this week or early next. The windows on Lot 7 should go in first of next week with veneer starting soon after.
Although we are still waiting on our final full grading permit, we can install storm piping and grade the site. We should have the full permit in about 2 weeks. With the full permit we can install sanitary sewer and water. We will start the foundation for the first home in about a month. Very exciting!